New Office IT Setup Checklist

Moving into new premises or fitting out an office? This is the complete UK checklist — what to install, in what order, with realistic costs and the mistakes that cost double.

By Triset Ltd — network installation & office IT delivery, Manchester · Reading time: 7 minutes

THE GOLDEN RULE

Cabling goes in first. Everything else in an office fit-out — floors, walls, furniture — makes cable access worse and more expensive. Structured cabling is the one item that must be installed at shell stage, before decorators and desk assemblers arrive. Retrofitting a cable run into a finished office can cost 2–3× the original price.

PHASE 1 — BEFORE THE FIT-OUT

PHASE 2 — CORE HARDWARE

PHASE 3 — WORKPLACE LAYER

PHASE 4 — SECURITY (DON'T SKIP)

REALISTIC BUDGETS

Office sizeTypical IT setup cost
5 desks£2,000–£4,000
10 desks£3,000–£8,000
25 desks£8,000–£20,000
50+ desks£20,000+ (survey essential)

Excludes computers themselves. Includes cabling, network hardware, configuration and labour.

THE 5 CLASSIC MISTAKES

QUICK SUMMARY